summer holiday; week 1,2 | map editor; initial research |
week 3 | specification; more research and draft basic design |
weeks 4-6 | complete detailed specification/design document |
week 7 | communication protocols |
weeks 8-9 | initial version of the server |
weeks 9-10 | client |
week 10 | progress report |
holiday | observer, module integration |
week 14 | complete primary objectives |
week 15 | finish documentation for primary and core objectives |
weeks 16-17 | debugging, documentation |
week 18 | complex agents, more experiments |
week 19 | compile existing documentation into presentation |
week 20 | project presentation |
week 20-22 | integrate latest experimental results into the report |
week 22 | final report |